Central Station's design was supposed to be selected from a competition in which five finalists presented futuristic designs that they hoped would become the signature station of the METRORail system.
But delays, cost overruns, the winner not being selected until September 2013 and fears that Central Station wouldn't be completed in time for the third quarter 2014 opening of the Green and Purple Lines to revenue service led METRO to scrap it last November and replace it with the generic stations platform
The Red Line is shut down this weekend from the Downtown Transit Center to the Northline TC to begin construction of the Central Station platforms.
But it would have been nice to see the signature Snohetta design going up.